| New Substation |
Works on the new substation to service Ta’ Maggi Industrial Park are rapidly underway. The necessary trench excavation and the laying of the cables have been completed. The transformer is also on the premises and will be in place shortly.
The works on this substation started approximately six weeks ago, after all the necessary road works permits were obtained and the setting up and fixing in position of all safety signage and barriers as per the Traffic Management Scheme. This project involves edge cutting of existing road surface with a rotary saw before the commencement of the trench excavation.
All the required quality assurance tests were performed along the process of work and all the material and workings were certified. This substation is indispensable for the park to benefit from constant and reliable electricity supply. Click here to download plans in PDF.
|
Works on the new substation to service Ta’ Maggi Industrial Park are rapidly underway. The necessary trench excavation and the laying of the cables have been completed. The transformer is also on the premises and will be in place shortly.